How to Make a House Electrical Layout Plan Before Wiring
A house electrical layout plan is the drawing that decides where every light, fan, switch board and socket goes before the walls are chased, and it is the cheapest place to get wiring right. This guide builds one the way a homeowner does with an electrician: a room-by-room point count for a typical Indian 2BHK, 6A and 16A sockets, board heights, circuits and the distribution board, board sizes in modules, the symbols on the drawing and what to leave room for.
Key takeaways
- Count points room by room from the furniture: our worked 2BHK has 17 light points, 6 fan points, 14 × 6A and 8 × 16A sockets, 3 AC and 2 geyser points.
- 6A for light loads, 16A for heavy ones: every geyser, AC, microwave and washing machine gets its own 16A point.
- One heavy appliance, one circuit: a typical 2BHK runs about ten outgoing MCBs plus spares on a 12 way board.
- Board heights are common practice, about 4 ft for switch boards; agree them with your electrician before boxes are fixed.
- Leave room for later: spare ways, empty conduit with a draw wire, and circuits planned for inverter backup and EV charging.
What a house electrical layout plan is
A house electrical layout plan is a floor plan with every light point, fan point, switch board, socket and appliance point marked on it, along with the circuit each one belongs to and where the distribution board sits, so the electrician wires exactly what you agreed. It is drawn before a single wall is chased.
The plan matters because wiring is the one part of a home you cannot change cheaply. A plate finish can be swapped years later without touching a wire. A socket in the wrong place, a missing 2 way switch at the bed or an AC point with no circuit of its own means breaking plaster.
Below, we build one for a typical Indian 2BHK, point by point. We make switches, sockets, plates and MCBs at our works in Marol, Andheri East, Mumbai. What we will not do is size your cables: that is a job for a licensed electrician on site.
Electrical layout for house: points for a typical 2BHK
The fastest way to start an electrical layout for a house is to count points room by room. A point is any place the electrician runs wire to: a light, a fan, a socket, an AC or a geyser. Our worked 2BHK below lands at 17 light points 6 fan and exhaust points 14 × 6A sockets 8 × 16A sockets plus 3 AC points and 2 geyser points.
Those numbers come from walking each room with its furniture in place. The table below breaks them out by room; treat it as a checklist to argue with, not a quota. A family that works from home needs more 6A points at the desk; a kitchen with an oven and an induction hob needs more 16A points on the counter.
Total electrical points per room in a worked 2BHK plan
Bar length is proportional to the total points per room in our worked example. A starting plan drawn by us for illustration, not a rule.
Count points from the furniture, not from the walls. A socket that ends up behind a wardrobe is a wasted point, and the extension lead that replaces it is the sign the plan fell short.
| Room | Light points | Fan points | 6A sockets | 16A sockets | AC or geyser |
|---|---|---|---|---|---|
| Living room | 4 | 1 | 4 | 1 | 1 AC |
| Master bedroom | 3 | 1 | 3 | 1 | 1 AC |
| Second bedroom | 2 | 1 | 3 | 1 | 1 AC |
| Kitchen | 2 | 1 exhaust | 2 | 4 | None |
| Common bathroom | 2 | 1 exhaust | 1 | 0 | 1 geyser |
| Attached bathroom | 1 | 1 exhaust | 0 | 0 | 1 geyser |
| Entrance, passage, balcony | 3 | 0 | 1 | 1 washing machine | Bell push |
| Total | 17 | 6 | 14 | 8 | 3 AC, 2 geyser |
How many sockets should each room have?
Plan one 6A socket for every device that stays plugged in at a spot plus one spare, and give every heavy appliance such as the fridge, microwave, geyser, AC or washing machine its own 16A socket on a circuit your electrician has sized for it. In our worked 2BHK that means three or four 6A sockets per bedroom and about four 16A points on the kitchen counter.
6A is for chargers, lamps, the TV, the router and a table fan. 16A is for anything that heats or drives a big motor: geyser, AC, iron, microwave, washing machine. A 16A plug will not fit a 6A socket. Our 6A vs 16A socket guide goes appliance by appliance.
Where a spot needs both, a combined socket saves a module: the KEMPS K193 6A and 16AX universal socket with shutter, or the VIZA V270 6 and 16A universal socket (2M). For a dedicated heavy point, the VIZA V263 16A socket. At bedsides and the study, a USB charger module such as KEMPS K207 or VIZA V305 frees a socket; see USB sockets for a switch board. Our 2 in 1 five pin sockets are 6A only, for 2-pin and 3-pin 6A plugs.
Never plan a heavy appliance onto a 6A socket and an adaptor. The plug fits, but the load still runs through contacts and wiring chosen for less, and the failure shows up later as heat.
Mark beds, sofas, the TV unit and the counter, then place points around them.
6A for light loads, 16A for anything that heats or drives a big motor.
Each AC and geyser on its own MCB, with spare ways left in the board.
Add switches at 1M and sockets at 2M, then round up to the next plate.
Electrical layout plan of residential building: room by room
An electrical layout plan of a residential building is drawn room by room, because each room has a different job. These are commonly planned points; your own list wins.
Living room Main lights and any cove or accent lights on separate switches, one or two fans with regulators, a TV wall with sockets at the height of the TV unit plus a TV socket (KEMPS K201) and a data point (KEMPS K205 RJ45 jack), and an AC point.
Bedrooms A door board for light, fan and regulator, and a bedside board with a 2 way switch for the main light, so it can be switched off from bed. That needs a matching 2 way switch at the door, such as KEMPS K102 10AX. Our 1 way vs 2 way switch guide explains the wiring. For the fan, a step regulator such as KEMPS K213 (4 step) or K214 (5 step); our fan regulator types article compares them.
Kitchen 16A sockets above the counter for each heavy appliance, a separate point for the fridge, a point for the chimney and the water purifier. Bathrooms Light and exhaust switches outside the door, and a geyser point with a DP switch.
Keep kitchen boards clear of the sink and the hob, and bathroom sockets well away from the shower.
For a shop, clinic or office floor, modular switches for office covers points per workstation and boards per floor.
What height should switch boards be in a house?
Switch boards in Indian homes are commonly fixed about 4 feet (around 1.2 m) above the finished floor, with bedside boards just above mattress height and low sockets about 1 foot up, but these are common practice rather than a fixed rule, so agree each height with your electrician before the concealed boxes go in.
Placement matters as much as height. Put the door board on the latch side of the door, the side your hand reaches as it opens, never behind the door. Keep every board in a room at the same height so they line up, and keep them clear of where the wardrobe, bed or sofa will stand. AC and geyser points sit high, near the unit, and are usually on a DP switch.
Typical heights above the finished floor, as commonly fitted
Bar length is proportional to the height shown. Kitchen counter sockets follow your counter, usually just above the backsplash. Common practice, not a code requirement.
Measure heights from the finished floor, after tiles, not from the bare slab.
How many circuits does a 2BHK need?
A typical 2BHK is split into about ten outgoing circuits: two for lights and fans, two for general sockets, one for the kitchen’s heavy points, one for each AC and one for each geyser, all fed from a double pole incomer. Add two spare ways for later and a 12 way distribution board usually fits.
Electricians work to one heavy appliance, one circuit, so a fault on the AC does not take the bedroom lights with it. Which rating goes where is covered in which MCB for home, and AC circuits in MCB for 1, 1.5 and 2 ton AC.
Our VIYONA MCBs are 10 kA breaking capacity to IS/IEC 60898-1: the 401 single pole and 411 double pole cover 6A to 32A. KEMPS K225 and K226 are modular SP and DP MCBs that fit a switch board. For the board itself, our distribution boxes include the 385 12 way double door and the 373 10–12 way SPN white line box.
Outgoing circuits in a worked 2BHK distribution board
Bar length is proportional to circuit count in our worked example: ten MCBs plus two spare ways behind a DP incomer, filling a 12 way board. Common practice, drawn by us; your electrician sets the real split and every MCB rating.
An MCB protects the wiring, not a person. Shock protection is the job of an RCCB, which is not in our catalogue; ask your electrician to plan both.
Board sizes in modules: from 1M to 18M
Once the points are fixed, each board’s size follows by arithmetic. A switch takes 1M, a socket or a fan regulator 2M, and the plate is the next size up: 1M, 2M, 3M, 4M, 6M, 8M, 12M or 18M. A bedroom door board with three lights, a fan switch, a regulator and a socket is 8M. Our modular plate sizes guide lists every width, and the plate size calculator does the sum for you.
Plate size for each board in the worked 2BHK
Bar length is proportional to plate size in modules: switches 1M, sockets, regulators and the 32A DP switch 2M. A count of 9 rounds up to 12M.
A count that falls between sizes is filled with a blank plate such as KEMPS K218, which is also how you leave room for a module you plan to add later. For finishes by room, see switch board design ideas; our KEMPS modular and VIZA modular ranges cover the sizes. Our plates fit all major modular switch systems and carry a 5-year warranty.
The box in the wall fixes the plate size. Decide the module count before the concealed boxes are set, and the plate can change finish any time afterwards without touching the wiring.
House electrical layout symbols and what they mean
House electrical layout symbols are small drawn marks that stand for each point on the plan: a circle with a cross for a light, a half circle for a socket, a small circle with a line for a switch, a rectangle for the distribution board. Every drawing should carry a legend; read that first.
| Item on the plan | Commonly drawn as | What to check |
|---|---|---|
| Light point | A circle with a cross through it | Which switch controls it |
| Ceiling fan | A circle with blades, or a circle marked F | Regulator on the door board |
| One way switch | A small circle with one short line | Board it sits on |
| Two way switch | A small circle with two lines | Its pair at the other end |
| 6A socket | A half circle, often marked 6A | Height and furniture |
| 16A socket | A half circle marked 16A, or filled in | Circuit it is on |
| Distribution board | A rectangle, often hatched | Number of ways |
| AC, geyser, TV, data | Letters such as AC, G or WH, TV, D | Dedicated circuit where needed |
When you check a drawing, go point by point with three questions: Is it on a board? Which circuit? What height? Ask for 6A and 16A to be marked differently, and for 2 way switches to be drawn in pairs.
Symbols differ between offices and software. If the drawing has no legend, ask for one before you sign it off.
Electrical wiring plan for house: what the drawing must show
An electrical wiring plan for a house goes one step past the layout: it shows which circuit each point is on, which route the conduit takes and which board it returns to.
A useful wiring plan carries circuit numbers beside every point, matching labels in the distribution board, conduit routes drawn along the walls and ceiling, the DB location with its number of ways, and every 2 way pair linked by a line. Keep conduit runs straight, vertical or horizontal from each board, so anyone drilling a wall later can guess where the pipe runs.
Before plastering, photograph every wall with a measuring tape held against the conduit. Those photos are the most useful document you will own the day you hang a frame or add a point.
Ask for the earthing to be shown and tested, not assumed. A socket is only as earthed as the wire behind it, and that cannot be seen from the plate.
Do not let the walls close until the wiring matches the plan point by point. Every change after plastering means chasing the wall again.
Common house electrical layout mistakes
Most layout regrets are small decisions made in a hurry on site. These are the ones that most often send people back to the electrician once they have moved in.
Board behind the door The switch you reach for is hidden when the door is open. No 2 way at the bed You walk to the door in the dark every night. Heavy loads on 6A points Microwave, iron or geyser on a socket not meant for them. AC sharing a circuit The AC trips the bedroom lights on a hot evening. Too few sockets Extension leads become permanent. No spare ways A new AC means a new board.
A switch that gets warm or a socket that sparks is often the plan catching up: a heavy load on a point wired for less. Our guide to a switch getting hot or socket sparking covers what to check first.
Mark it on the plan and a change costs a line of ink; after plastering it costs a wall.
Walk every room with the electrician before chasing starts. Stand where you will stand, reach for where the switch will be, and mark changes on the drawing there and then.
Home electrical planning for later: inverter, EV charging and spare conduit
Leave room for what the home will need later, even if you install none of it now. Three provisions are cheap before plastering and expensive after.
Inverter backup Decide which points run on backup, typically some lights, the fans and a few sockets, and ask for them on separate circuits so the inverter can be fed from them without rewiring. Mark a ventilated spot near the distribution board for the inverter and battery.
EV charging A charger needs a dedicated circuit from the board to the parking spot, sized to the charger its maker specifies, not a borrowed socket. Lay an empty conduit to the parking spot now; in a housing society, check what the building allows.
Spare conduit Run empty pipes, with a draw wire, from the board to the TV wall, the study and any room you might convert, and leave spare ways in the distribution board.
Backup circuits and the EV point change the load on your connection. Your electrician checks them against the sanctioned load before they are added.
Choosing fittings once the plan is fixed
With points, circuits and board sizes on paper, the fittings are a shopping list. Our guide to choosing a switch board covers the order: size, then rating, then finish.
We make three series. KEMPS modular switches and sockets, from the K102 10AX 2 way switch to the K116 32AX DP switch with indicator for a geyser or AC point; browse KEMPS switches and sockets. VIZA modular, including the V1250 32A DP switch with indicator and the V263 16A socket; see VIZA switches and sockets. VIYONA for MCBs, distribution boxes and VIYONA switches and sockets.
For lights and fans, 6A or 10AX switches are the right rating. Everything is made at our Mumbai works under an ISO 9001:2015 certified process. We do not sell online: take your list to a dealer, call us, or visit.
Hand the dealer a list by board, with plate size, series and each module code, and the whole house is priced in one visit.
Once the points are counted, our electrical accessories list with prices turns the plan into a shopping list, item by item at MRP.
FAQs
How do I make an electrical layout plan for my house?
How many electrical points are needed for a 2BHK?
What is the standard height of a switch board from the floor?
How many MCBs are needed for a 2BHK flat?
What symbols are used in a house electrical layout?
Should I plan for an inverter and EV charger now?
Why buyers choose Vinayak Electricals
- Everything on the plan from one catalogue — switches, sockets, plates, regulators, MCBs and distribution boxes across KEMPS, VIZA and VIYONA.
- VIYONA MCBs at 10 kA breaking capacity to IS/IEC 60898-1, single pole to four pole, with isolators and boards from 4 way to 16 way.
- Plates from 1M to 18M that fit all major modular switch systems, UV-protected so they do not turn yellow, with a 5-year warranty.
- Made in our own works in Marol, Andheri East, Mumbai, under an ISO 9001:2015 certified process, manufacturing since 1995.
- 2000+ products in-house, so a whole house can be listed by code and priced at one dealer counter.
- Buy from a dealer, by phone or by visiting — our team helps turn a layout plan into a product list by code.
Turn your layout plan into a product list
Browse switches, sockets, plates, MCBs and distribution boxes by code across KEMPS, VIZA and VIYONA, then take the list to a dealer or call our team.
Browse products