Skip to content
Planning guide

Electrical Load Calculation for House Wiring, Worked for a 2BHK

Electrical Load Calculation for House: 2BHK Example

Electrical load calculation for house wiring is two sums: add the watts of everything wired in to get the connected load, then add only what runs together at your busiest hour to get the peak, which is the figure that sizes the main MCB and tells you whether your sanctioned load still fits. Below we work it through for a typical 2BHK with three ACs and two geysers, convert kW to amps, check each circuit, show when the load points to three phase, and list the MCBs and isolators we make for the main switch.

Key takeaways

  • Connected load — the sum of rated watts of everything wired in. Our worked 2BHK: about 15.5 kW.
  • Peak load — only what runs together at the busiest hour. Same 2BHK: about 6.8 kW on a summer evening.
  • Amps — watts ÷ 230 for single phase: 6.8 kW is about 29 A, so a 40A main gives headroom.
  • Per circuit — each AC and geyser on its own MCB; check every circuit the same way.
  • Recalculate before adding an AC, geyser or EV charger; check the sanctioned load on your bill.
15.5 kWConnected load, worked 2BHK
6.8 kWSummer evening peak
29 APeak current at 230 V
₹435VIYONA 412 40A DP MCB

Electrical load calculation for house: the short answer

An electrical load calculation for a house adds up the rated watts of every appliance and light you will connect, which gives the connected load, then estimates which of them run at the same time, which gives the peak or maximum demand. The connected load tells you how much is wired in. The peak decides the main MCB, the sanctioned load you apply for, and whether single phase is enough.

We work both numbers through for a typical 2BHK below. With three 1.5 ton ACs, two storage geysers and a normal kitchen, the connected load comes to about 15.5 kW, while the realistic peak on a summer evening is about 6.8 kW. The gap between those two figures is why nobody sizes a main switch by adding up everything on the list.

Every wattage here is a typical figure from our appliance power consumption chart, not a measurement of any model; your appliances’ rating plates give the real ones. We make the MCBs, isolators and distribution boxes the result feeds into, at our works in Marol, Andheri East, Mumbai. The final design is a licensed electrician’s job.

What is connected load and how is it calculated?

Connected load is the total of the rated power of every appliance, light and fixed equipment wired into a home, calculated by listing each item with the watts printed on its rating plate, multiplying by how many there are, adding them all, and dividing by 1,000 to express the result in kilowatts.

It counts everything connected, whether or not it runs together: the AC in the guest room that is on ten nights a year counts the same as the fridge that never stops. That is why connected load is always the larger figure.

Where to find the watts: the rating plate, the carton, the BEE star label or the manual. If a plate gives amps instead, multiply by 230 for a single phase appliance. For an AC, use the input watts on the outdoor unit’s plate, not the tonnage.

Typical ranges for every common appliance, from a 9 W LED lamp to a 3,000 W geyser, are in our appliance power consumption chart; we use those figures throughout this page.

Tonnage is cooling, not watts. A 1.5 ton AC’s electrical input is on its nameplate, and two makers’ 1.5 ton units can differ.

Worked 2BHK load list (typical watts; your rating plates give the real figures)
ItemWatts eachQuantityConnected (W)On at evening peak (W)
1.5 ton AC1,50034,5004,500
Storage geyser2,00024,0000
Induction cooktop2,00012,0001,500
Microwave and mixer1,200 and 7501 each1,9500
Iron, washing machine, pump1,000, 500, 7501 each2,2500
Fridge2501250250
Ceiling fans753225225
LED lamps (our 1065)917153153
TV, laptop, router80, 50, 101 each140140
Total15,4686,768

How to calculate electrical load step by step

To calculate the electrical load of a house step by step, list every appliance by room, write the watts from each rating plate, multiply by quantity, add them for the connected load, mark which loads run together at your busiest hour, add those for the peak, and divide the peak by 230 to get the current your main MCB must carry.

Step 1 List by room, using your layout plan. Step 2 Watts from each plate. Step 3 Watts × quantity. Step 4 Add all: connected load. Step 5 Pick the busiest hour, often a summer evening or a winter morning. Step 6 Add only what runs then: peak. Step 7 Peak ÷ 230 = amps at single phase.

A spreadsheet with four columns, appliance, watts, quantity and “on at peak?”, does all of it. Our house electrical layout plan gives a worked 2BHK point list to start from.

Keep the list. It is the same list the supply company asks for when you apply for more load, and the one your electrician needs to plan circuits.

Do the list before the wiring starts. A load that was never on paper is the one that ends up on a socket and wire meant for less.

List everything

Watts from each plate, room by room.

Two sums

Connected load, then the busiest-hour peak.

Watts ÷ 230

Turns the peak into amps for the main.

Redo it

Every new AC, geyser or charger changes the sum.

Electrical load calculation for a 2BHK: worked example

In our worked 2BHK, with three 1.5 ton ACs, two storage geysers, a full kitchen, a washing machine, a water pump, three ceiling fans and 17 LED light points, the connected load adds up to about 15,468 W, or roughly 15.5 kW, with the ACs and geysers making up more than half of it.

The list, at typical watts: 3 ACs × 1,500 W = 4,500; 2 geysers × 2,000 W = 4,000; induction 2,000, microwave 1,200 and mixer 750 = 3,950; iron 1,000, washing machine 500 and pump 750 = 2,250; fridge 250; 3 fans × 75 W, 17 LED lamps × 9 W, plus TV, laptop and router = 518.

Connected load of the worked 2BHK, by group (W)

3 ACs, 1.5 ton4,500 W
2 storage geysers4,000 W
Kitchen: induction, microwave, mixer3,950 W
Iron, washing machine, pump2,250 W
Fans, LED lights, TV, router, laptop518 W
Fridge, running250 W

Typical watts from our appliance power consumption chart; the LED lamps are our 9 W 1065 and the iron our 1000 W range. A worked example, not a measurement. Bars to scale with 4,500 W as the full bar.

Lights, fans and electronics, the things that run longest, are about 3% of the connected load. Heating and cooling are most of the rest.

How much kW load is needed for a 2BHK?

In our worked 2BHK the peak load is about 6.8 kW, on a summer evening with all three ACs, the fridge, fans, lights and the induction cooktop on together, against a connected load of about 15.5 kW, so the house needs a supply and main switch sized for roughly 7 kW, not 15.

The two busy hours, at typical watts: Evening 3 ACs 4,500 + induction 1,500 + fridge 250 + fans 225 + lights 153 + TV, laptop and router 140 = 6,768 W. Morning 2 geysers 4,000 + induction 1,500 + mixer 750 + fridge 250 + fans and lights about 200 = 6,700 W.

Worked 2BHK: connected load vs the two busiest hours (W)

Connected load15,468 W
Summer evening peak6,768 W
Morning peak6,700 W
Evening without ACs2,268 W

Our arithmetic from the worked list, typical watts, not a measurement. Bars to scale with 15,468 W as the full bar.

Take the ACs out and the evening drops to about 2.3 kW; the morning, driven by the geysers, barely moves. A 2BHK with fewer ACs or a single geyser lands lower. Your own list, not ours, gives your figure.

Connected load vs maximum demand: why the peak is lower

Maximum demand is lower than connected load because appliances do not all run at once and many cycle on and off: the geyser heats for half an hour, the iron for fifteen minutes, the AC compressor slows once the room is cool, so the highest load actually drawn is a fraction of everything wired in.

In our worked 2BHK, the peak is about 44% of the connected load. That is our example, not a factor to apply to every house. A family that runs two geysers and the washing machine heater together, or three ACs and an induction cooktop at dinner, pushes the peak higher.

Three habits keep the peak down without giving anything up: stagger the geysers, run the washing machine outside the AC hours, and switch the geyser off once the tank is hot. Each of these also helps the bill; our guide to how to calculate an electricity bill turns units into rupees.

Some meters record maximum demand. If your bill shows it, compare that figure with your own estimate: the meter is the better witness.

A peak estimate is a judgement, not a measurement. Write down which loads you assumed were on together, so the electrician can challenge it.

Sanctioned load vs connected load: which figure do you need?

You need both: connected load is the total you calculate from your appliance list, while sanctioned load is the figure in kW or kVA your supply company has agreed to supply, printed on your bill, and the calculation tells you whether the sanctioned figure still covers how your home actually uses power.

Supply companies differ on how they assess it. Some look at the connected load declared on the application, others at the maximum demand the meter records. Fixed charges in many tariffs depend on the sanctioned figure, so it is worth getting right in both directions.

If your peak estimate sits well above the sanctioned load, for example after adding two ACs, the supply company will usually expect an application to raise it, often with a load list and a test report from a licensed electrical contractor.

What sanctioned load means, where it sits on the bill and kW vs kVA are explained in our single phase vs three phase guide; we have not repeated them here.

Rules on sanctioned load, penalties and charges differ by state and change over time. Check your own supply company’s current rules.

From kW to amps: sizing the main MCB

To turn a load in kW into the current the main switch must carry, divide the watts by 230 for a single phase home, so our worked 2BHK’s 6.8 kW peak is about 29 A, which is why a 40A double pole main gives sensible headroom while a 32A one would run close to its limit.

The arithmetic: 6,768 W ÷ 230 V ≈ 29.4 A. Everything on at once would be about 67 A, which no one sizes for. A small flat with lights, fans and a couple of ACs commonly runs on a 32A or 40A incomer; a larger home moves to 63A, as our which MCB for home guide sets out.

MRP of our double pole main switch options (₹)

DP isolator 40A (442)₹230
DP isolator 63A (443)₹290
DP MCB 6–32A (411)₹350
DP MCB 40A (412)₹435
DP MCB 63A (413)₹530

MRPs from our current catalogue, bars to scale with ₹530 as the full bar. All MCBs in our VIYONA 10 kA range are 10 kA, to IS/IEC 60898-1.

VIYONA 412 is a 40 A double pole 10 kA MCB at ₹435 MRP. An isolator can be the main only where every circuit below has its own MCB.

Load per circuit: checking each MCB

Load per circuit is the sum of what each circuit carries at its busiest, and it decides that circuit’s MCB and wire: each AC and each geyser gets its own circuit, so one appliance’s current sits on one MCB, while lights, fans and general sockets are split over a few circuits so none runs near its limit.

In the worked 2BHK, that means about ten outgoing circuits: two for lights and fans, two for general sockets, one for the kitchen’s heavy points, three for the ACs and two for the geysers, plus two spare ways on a 12 way board. Our layout guide draws the same split.

Check each circuit the same way as the house: add its loads, divide by 230, and compare with the MCB. A kitchen circuit carrying the induction (2,000 W), microwave (1,200 W) and mixer (750 W) together reaches about 17 A, more than a 16A circuit should carry; electricians commonly split such loads.

Matching the wire to each MCB is in which wire for AC and geyser; the box size for the circuit count is in our MCB box size list.

Never fit a bigger MCB to carry more load on the same wire. The MCB protects the wire; the wire, not the MCB, sets the limit.

Single phase or three phase: when the load decides

The load calculation decides single vs three phase when the peak current on one phase gets uncomfortably large, as it does in homes with several ACs, an instant geyser or a three phase motor, or when the supply company’s rules ask for three phase above a load limit in its supply code.

Our worked 2BHK, at about 29 A peak, is a comfortable single phase home. Add a fourth AC and an instant geyser and the peak can pass 45 A, which is where an electrician starts discussing a three phase connection or a higher single phase incomer.

In a three phase home the same list is split across the R, Y and B phases, ideally one AC per phase, so each phase carries about a third. The three phase board needs a four pole main: our VIYONA 461 four pole isolator is ₹480 MRP and the 432 four pole MCB ₹855.

When it is worth switching, and how loads are balanced, is covered in single phase vs three phase.

Three phase gives headroom, not cheaper units. You still pay for every unit you use.

Adding an AC, geyser or EV charger: recalculate first

Before adding an AC, a geyser, an induction cooktop or an EV charger, rerun the load calculation, because each one adds kilowatts to the peak, needs its own circuit, MCB and wire, may need a spare way in the board, and can push the total past your sanctioned load or your main MCB’s rating.

One more 1.5 ton AC adds about 1.5 kW to a summer evening, roughly 6.5 A. In the worked 2BHK that takes the evening from about 29 A to about 36 A, past a 32A main and still inside a 40A one.

An EV charger is a long, heavy load that may run for hours overnight; its maker specifies the circuit, and the electrician checks it against the sanctioned load. Backup circuits for an inverter change the picture too; see inverter for home.

If the board has no spare way, a new appliance means a bigger box. Our VIYONA SPN white line box runs from ₹380 for 2–4 way to ₹950 for 16–18 way.

Leave two or three spare ways and a little headroom on the main when the house is wired. The next AC then needs a circuit, not a new board.

Common load calculation mistakes

The commonest load calculation mistakes are adding up MCB ratings instead of appliance watts, using AC tonnage as if it were kilowatts, forgetting the geysers and the washing machine heater, sizing the main for the connected load instead of the peak, and never redoing the sum when a heavy appliance is added.

Adding MCB ratings Ten MCBs of 16A do not mean 160 A of load. Tonnage as kW A 1.5 ton AC is not 1.5 kW by definition; read its plate. Forgotten heaters Geysers and washing machine heaters set the morning peak. Connected = peak Oversizes the main and the application. One-time sum A house’s load grows; the calculation should too.

A careful list also shows where the cheap savings are. Our worked example’s lights and fans are a sliver of the load; the geysers and ACs are where timing and settings matter.

For the cost of wiring a home sized this way, see our guide to house wiring cost.

A load calculation guides the design; it does not replace it. Cable sizes, MCB ratings and the earth are set by a licensed electrician on site.

FAQs

How do you calculate the electrical load of a house?
Add the rated watts of every appliance and light for the connected load, then add only what runs together at the busiest hour for the peak, and divide the peak by 230 to get the current for a single phase main switch.
How much kW load is required for a 2BHK flat?
In our worked 2BHK with three ACs and two geysers the peak is about 6.8 kW against a connected load of about 15.5 kW; a flat with fewer ACs or one geyser needs less, so make your own list.
What is the difference between connected load and sanctioned load?
Connected load is the total rating of everything wired into your home, while sanctioned load is the kW or kVA your supply company has agreed to supply, printed on your electricity bill.
How many amps is a 5 kW load?
A 5 kW load on a single phase 230 V supply draws about 21.7 A, from 5,000 watts divided by 230 volts.
Which main MCB is needed for a 7 kW load?
A 7 kW single phase peak is about 30 A, so a 40A double pole main gives sensible headroom; VIYONA 412, a 40A double pole 10 kA MCB, is ₹435 MRP, and your electrician confirms the rating.
Do I need three phase for 10 kW?
Not always; it depends on your peak, not your connected load, and on your supply company’s rules, but a 10 kW peak is about 43 A on single phase, which is where many electricians start discussing three phase.

Why buyers choose Vinayak Electricals

  • 10 kA VIYONA MCBs from 6A to 63A, single to four pole, made at our works in Marol, Andheri East, Mumbai.
  • Double pole mains: VIYONA 412 40A MCB at ₹435 and 442 40A isolator at ₹230 MRP.
  • SPN white line MCB boxes from 2–4 way (₹380) to 16–18 way (₹950), with room for spare ways.
  • MCBs to IS/IEC 60898-1 under BIS licence CM/L-2544151.
  • MRPs published openly; sold through 500+ dealers with delivery across India.
  • Manufacturing in Mumbai since 1995; ISO 9001:2015 certified.

MCBs and isolators for the main switch

See codes, poles and MRPs for our VIYONA MCBs and isolators, then order through a dealer or call us.

View MCBs and isolators

Keep reading

All articles

Our Series

All products

Become a dealer or distributor

Join a network built over three decades. Territory support, scheme pricing and a full product catalogue behind every order.